Update: 4/16/21 - This project will be conducted in phases with a total of 3 phases. Properties listed in the weekly description will indicate what phase of work is being conducted. By clicking on the phase descriptions below, you can learn more about what can be expected in each phase. Since this project is phase work, it is very important to keep in mind you will see crews visit your street on...Read more
News & Announcements
Learn about Customer Service Announcements, News, Job Opportunities, and Project Updates.
April 16, 2021 - 2:05pm in Project Overview
Status Update (chronological): Update |
April 16, 2021 - 1:18pm in Project Overview
Update: 4/16/21 Work Completed between 4/12/2021 and 4/16/2021 Continued cleanup and landscape restoration Paving restoration work in County Line Road at night time, including saw cutting, and testing of the new sewer mains. Work Projected for next week Continuing cleanup and landscape restoration Continuing paving restoration work and sewer testing in County Line Road at night time. PAST UPDATES...Read more Status Update (chronological): Update |
April 7, 2021 - 1:04pm in Project Overview
Update: 4/7/21 Paving restoration associated with the new water main that was installed in your neighborhood is scheduled to begin on or around Tuesday, April 13 th . Lawn and grass areas will be restored following paving. Please keep in mind that schedules are weather dependent and subject to change. Thank you for your patience as we work to complete this project. Past Updates 3/12/21 Work...Read more Status Update (chronological): Update |
March 12, 2021 - 2:55pm in News
BMC CAP will be hosting their next meeting virtually on 4/20/21Read more |
March 9, 2021 - 3:17pm in Project Overview
Update: 3/9/21 - PADEP has directed HWSA to evaluate the need for public sewer in this area. In 2016-2017 HWSA performed a survey to gauge property owner interest in the Authority constructing a sewer extension. At that time, there was not a majority interest so the Authority did not move forward with the project. Interest in a sewer extension will be reassessed as part of this evaluation, but...Read more Status Update (chronological): Beginning the week of 3/8/21 |
March 3, 2021 - 9:10am in Project Overview
Update 1/21/21 - Work is scheduled to begin in early March. Exterior preconstruction videotapping is being conducted in the meantime. Property owners will be contacted directly by the contractor (DOLI) to schedule interior inspection with existing interior conditions being documented at that time. Any residents impacted by the MIRIA house connection project are asked to contact the Authority main...Read more Status Update (chronological): Work to begin in early March |
February 3, 2021 - 11:06am in Project Overview
Update: 2/3/21 Work completed between 1/19/2021 and 2/2/2021: Completed majority of finish coating of tank exterior and foundation structures. Some repairs and touch-ups will be required in the spring. Completed installation of gate valves and altitude valve. Manufacturer start-up is still to be scheduled. Completed majority of electrical work, including SCADA system. Completed post-construction...Read more Status Update (chronological): Update |
January 25, 2021 - 8:37am in News
Through a tremendous collaborative effort between the Commonwealth, the MIRIA, the HWSA and Horsham Township, HWSA is pleased to announce the reimbursement of the PFAS surcharge implemented in 2016. Checks are anticipated to be issued in October!! Any resident with public water that has paid a PFAS surcharge should anticipate a check. Watch your mail closely in the coming weeks.Read more |
January 15, 2021 - 2:27pm in Project Overview
Updates: Information will be available soon! Past Updates:Read more Status Update (chronological): TBA |
October 16, 2020 - 2:44pm in News
HWSA water customers will soon be receiving their PFC Surcharge Reimbursement checks - This FAQ document is to help answer some anticipated questions What is the PFC surcharge? The PFC Surcharge is an additional charge that went into effect for all HWSA water customers in September of 2016. The surcharge was instituted to cover the cost of reducing the average concentration of PFOS and PFOA in...Read more |