Area A Flow Transfer

Update 10/25/19 - Area A Transfer tentative construction schedule announced Click here for construction schedule

Mobilization for the gravity sewer portion of the project is scheduled for early December and will be starting on Keith Valley Road, working towards County Line Road.  A schedule for the County Line Road overnight work has not yet been established, but will be posted as soon as it becomes available.

Update 10/25/19 – County Line Road Area Infrastructure Improvements in conjunction with Area A Flow Transfer tentative construction schedule announced! - Click here for construction schedule

Mobilization for the portion of the sanitary sewer and water main replacement work from Springbrook to Latchstring Lane via Sherwood Lane is tentatively scheduled for early January 2020.  The schedule for the installation of the pump station at the end of Springbrook Lane has not yet been established but will be posted as soon as it becomes available.

Past Updates:

10/15/19 - Notice to proceed for the Authority’s Area A Flow Transfer Project and the first phase of the County Line Road Area Infrastructure Improvement projects has been issued.  The project is scheduled to be ongoing throughout the winter with completion anticipated in late April/early May 2020.  An anticipated construction sequence will be posted in the coming weeks.

WORK IS EXPECTED TO BEGIN WITHIN THE NEXT SEVERAL WEEKS AND WILL BE ONGOING FOR A PERIOD OF APPROXIMATELY 6 MONTHS.  As with all construction projects, weather and other factors can cause schedules to change faster than we can advise via standard mail communication, so keep an eye on this project via our website.

Work Area 1 - Is a water and sewer construction project that may affect access to properties via County Line Road.  the work involves new water and sewer mains in the following streets: Springbrook Lane, Maple Avenue from Springbrook to Sherwood Lane, Sherwood Lane to Latchstring Lane, Latchstring Lane to County Line Road, and then continuing west on County Line Road.  Please view the project map to see the impacted area.

Work Area 2 - is a sewer construction project that may affect access to County Line Rd from Latchstring Lane, west through the intersection of 611 to the PECO substation located approximately 1600' west of 611.  Work will proceed along the boundary of the Horsham Air Guard Station, on the Horsham Township's Strawbridge Park and adjacent private property, to Keith Valley Road.  Please view the project map to see the impacted area.

This project includes 8,300 linear feet of 12' gravity sewer, 3,200 linear feet of 6" force main and approximately 3,100 linear fee of 8" watr main.  A new sewer pump station will be constructed on the Hideaway Swim Club Property, and  the existing County Line Road pump station will be decommissioned.

All work on County Line Road will be performed at night between the hours of 8:00 PM and 5:00 AM, during this time traffic control will be in place, including lane closures and flagging - this may result in delays in the area.  As always, access to emergency services will be maintained.  

All work on Easton Road (Route 611) has a contruction time period limited to night hours.

Work hours for this project with the exception of County Line Road and Easton Road are Monday thru Friday 7am to approximately 6pm, no earlier than 8am on Saturday and no work is permitted on Sunday.

 

 

 

Status Update (chronological): 

Work beginning soon!