English Village Apartments Sanitary Sewer Replacement

Last Week (5/13/2019 to 5/17/2019)

  • Contractor installed sewer from MH-4 to MH-5. 
  • Contractor installed MH-5
  • Contractor began sewer installation from MH-5 towards MH-6.
  • Contractor connected sewer from MH-3 to E-2

This Week (5/20/2019 to 5/24/2019)

  • Continue sanitary sewer installation from MH-5 to MH-6.
  • Set MH-6 and MH-7.  Connect sewer in between
  • Continue sanitary sewer installation from MH-6 towards MH-9 (towards the Shops at English Village)

Status Update (chronological): 

English Village Apartments (EVA) - Work to begin Monday 3/18/19