
Update: 3/15/22
Week of 3/7/22
- Final well abandonments were completed
Future work
- All necessary restoration will take place in the spring, as weather permits
Past Updates:
3/2/22
Week of 2/21/22
- The well driller abandoned eight wells.
- All houses are connected.
Week of 2/28/22
- Well abandonments will continue, weather permitting.
2/21/22
Week of 2/14/22
- Last week the plumber connected 5 houses.
- The well driller pulled pumps last week, but did not abandon any wells.
Week of 2/21/22
- Final house connection of this project will be completed
- Well abandonments are scheduled, weather dependent.
2/15/22
Week of 2/7/22
- 8 houses connected
- A total of 27 houses have been connected
- 15 wells were abandoned
Week of 2/14/22
- Connection is anticipated for the 5 remaining homes
- Well abandonment will continue
2/7/22
Week of 1/31/22
- The plumber connected 5 houses
- 19 houses have been connected to date
Week of 2/7/22
- Additional connections are scheduled for the upcoming week
- The well driller is expected to start abandoning wells this week, weather dependent
2/1/22
Work completed as of 2/1/22
- 15 homes have been connected to date
- The well driller began pulling well pumps from connected homes
Work projected
- 5 connections scheduled the week of 2/1/22
- Well abandonments are anticipated to begin during the week of 2/7/22 or 2/14/22, weather dependent
1/27/22
- The contractor completed service connections for all 33 residential properties
- Houses connections were made on Privet Road and Prospect Avenue - 10 homes have been connected so far
- House connections will continue this week
- The well driller has begun pulling
1/19/22
Week of 1/10/22
- The contractor (Doli) continued working on service connections. 15 services were installed to homes on Norristown Rd, Sawmill Ln, Edgewood Ave, Willowbrook Rd, Evergreen Rd, Davis Grove Rd, and Avenues C and D. House connections continue to follow service connections.
Week of 1/18/22
- Service and house connections continue