Update: 5/19/23 – During the week of 5/22/23, crews will be working on Harcourt Lane. If time permits at the end of the week, crews will be working on Holly Drive and Butternut Drive.
Past Updates:
4/11/23 - Mainline lining is scheduled to begin early to mid-May and t-lining is schedule to begin the week of June 5, 2023. Work schedules are approximate and may change.
2/27/23 - On Wednesday 3/1/23, crews will be performing CCTV in the sewer mains on Harcourt Lane and Butternut Drive
2/6/23
During the week of 2/6/23, crews will be on the following streets:
- Butternut Drive
- Holly Drive
- Springbrook Lane
- County Line Road
Also, there will be a crew working on manhole rehabilitation near the air base.
1/13/23 - Sewer main and lateral cleaning, flushing and CCTV inspection will occur next week on Buckman Dr, Maurice Ln, Latchstring Ln, Brumar Dr, Winding Rd, and Sherwood Ln. There should be no service interruptions.
1/5/23 - Contract work for the Springbrook area is scheduled to begin the week of January 9, 2023. Prior to the work beginning, the contractor will perform pre-construction televising. Work is expected to begin on Harcourt and Maurice Lanes, and service interruptions are not anticipated. The contractor will be performing sewer main and lateral cleaning, flushing and CCTV inspection.
12/28/22 – The work to be done under this contract consists of all labor, equipment and materials to televise, clean and repair the sanitary sewer system in the Springbrook Area. The work includes but is not limited to erosion and sediment control measures, restoration of disturbed areas, pavement restoration, traffic control, bypass pumping, as well as pre-construction and post-construction televising. Questions or concerns regarding this project should be directed to the Authority office at 215-672-8011.