Treatment System Update

Work Completed up to 9/6/19

•Well 19 – Completed concrete pads for exterior stairs
•AQUA IC – Completed Building and Roof excluding downspouts and gutters, staked out the lowering of the water lines
•Completed various Punch List items at Wells 2, 20, 22, 4, and 19.
•Well 22 – Competed installation of Heat Trace and Insulate
•Completed various Punch List items at Wells 2, 20, 22, 4, and 19.
• AQUA IC – Started conduit and panel installation
• Well 22 – Competed installation of Heat Trace and Insulate
•AQUA IC – HVAC equipment including exhaust fan, heaters, and louvers were installed

 

Work Projected for Week of 9/9/19

•Well 19 – Beginning installation of exterior stairs and railings
•AQUA IC -  Lowering the water lines as marked by the stakeout, Interior Piping installation to follow (probably 9/16)
•Well 2 – Addressing needed VFD repairs
•AQUA IC – Starting the wiring on installed electrical equipment
 

Transitioning from the Short Term to Long Term Plan      

Projected Completion Schedule

PFAS Action Act of 2019 -

                       

Below please click on each individual well number to view a video of the progress

Well 2               Well 4                  Well19              Well20                 Well 22

HORSHAM PFC TREATMENT SYSTEMS  SCHEDULE - GROUP 2

Status Update (chronological): 

Treatment Systems Update