Treatment System Update

Treatment Systems Update

Projected Completion Schedule

Transitioning from the Short Term to Long Term Plan

Week of 3/11/19

  • Well 2 – demoed and installed new FRP Aeration Building
  • Well 20 –installed new chlorine analyzer
  • Well 22 – re-anchored backwash tank
  • Well 4 – installed new chlorine analyzer, delivered the first load of interior piping
  • Well 19 –finished installing valve vault, connected drain piping to manhole
  • Aqua Interconnect – no work
  • Well 2 – Installed Antenna for communication to HWSA system
  • Well 20 – Installed Antenna for communication to HWSA system
  • Well 19finished installation of lighting, continued conduit installation and wiring, started demo of existing equipment

Week of 3/18/19

  • Well 2 – continuing reconnecting pipe and equipment in new FRP Aeration Building
  • Well 20 – no work planned
  • Well 22 – no work planned
  • Well 4 – starting installation of interior piping
  • Well 19 – continuing installation of valve vault including associated exterior piping and continuing exterior piping for backwash source
  • Aqua Interconnect – no work planned
  • Well 2 – reconnecting equipment and wiring in new FRP Aeration Building
  • Well 19finishing conduit, wiring, and demo of existing equipment
  • Well 2 – starting installation of HVAC equipment in new FRP aeration building
  • Well 19 – starting installation of heat trace and insulate for backwash piping

Below please click on each individual well number to view a video of the progress

Well 2               Well 4                  Well19              Well20                 Well 22

HORSHAM PFC TREATMENT SYSTEMS  SCHEDULE - GROUP 2

Status Update: 

Treatment Systems Update