Treatment System Update

Work Completed up to 10/11/19

  • Well 19 – Started installation of exterior stairs and railings, Placed topsoil and hydroseeded
  • AQUA IC – Lowered the water lines per Change Order #11, completed installation of interior piping and painted the piping, completed installation of the sanitary sewer from inlet to new manhole constructed by developer’s contractor, started installation of chlorination equipment including taps of the interior piping
  • AQUA IC – Started the wiring of installed electrical equipment including lighting and panels, Powered site on 10/8,

Work Projected for Week of 10/14/19

  • Well 19 – Beginning installation of exterior stairs and railings
  • AQUA IC – Complete final tie-in by the interconnect and test water lines. Based on progress, schedule Carbon Delivery

Work Projected for Week of 10/21/19

  • AQUA IC – Finish Site Work, Complete concrete curb, paving, seeding, and grading

Work Projected for Week of 10/28/19

  • Address Punchlist items
 

Transitioning from the Short Term to Long Term Plan      

Projected Completion Schedule

PFAS Action Act of 2019 -

                       

Below please click on each individual well number to view a video of the progress

Well 2               Well 4                  Well19              Well20                 Well 22

HORSHAM PFC TREATMENT SYSTEMS  SCHEDULE - GROUP 2

Status Update (chronological): 

Treatment Systems Update