Treatment System Update

Work Completed during Week of 6/24/19

  • Well 19 – Finished paving the new driveway
  • AQUA IC – HVAC equipment including exhaust fan, heaters, and louvers were installed

Work Completed during Week of 7/1/19

  • Well 4 – repaired PV-2 with Calgon Carbon
  • Completed various Punch List items at Wells 2, 20, 22, 4, and 19.

Work Projected for Week of 7/8/19

  • Completing various Punch List items at Wells 2, 20, and 22.

Transitioning from the Short Term to Long Term Plan      

Projected Completion Schedule

PFAS Action Act of 2019 -

                       

Below please click on each individual well number to view a video of the progress

Well 2               Well 4                  Well19              Well20                 Well 22

HORSHAM PFC TREATMENT SYSTEMS  SCHEDULE - GROUP 2

Status Update (chronological): 

Treatment Systems Update