Treatment Systems Update

Treatment Systems (Blooming Glen)

  • Completed building footers at Well 2 (excavation, rebar and concrete) - pic attached
  • Completed form work on Well 2 Backwash Tank – pic attached
  • Started installing block for Well 22 building – pic attached
  • Completed asbestos removal at Wells 4 & 20

County Line Road Interconnect

  • Completed building block work – pic attached
  • Installed top bond beam.

Week of 2/19/18

  • Apply foundation coating at Well 22
  • Install trench drains at Well 22
  • Backfill foundation at Well 22
  • Prepare floor slab at Well 22
  • Install E&S at Well 4
  • Start demo work at Wells 4 & 20
  • Start installation of top roofing plates and trusses

Status Update: 

Treatment Systems Update

For questions or to report problems: 215-672-8011