Treatment Systems Update

Treatment Systems

Saturday work is expected at Wells 19 & 20 in order to wrap up rebar installation for the columns at Well 19 and the floor slab at Well 20. The concrete pour is scheduled for Tuesday.

  • Well 2 – no work
  • Well 20 – backfilled footer excavation, installing trench drains
  • Well 22 – no work
  • Well 19 – installed footing and column rebar

PSI Pumping Solutions

  • Well 2 & 22 – underground conduit, transformers set

Water Mains

  • Paving restoration on County Line Road, painted hydrants

County Line Road Interconnect

  • Interior HVAC
  • Removed stockpiles from site

Week of 4/23/18

  • Well 19 – continue rebar for building columns – concrete pour scheduled for Tuesday
  • Well 20 – continue rebar for floor slab – concrete pour scheduled for Tuesday, Calgon Filter delivery on Thursday
  • Wells 2 & 22 – finish conduit, start pulling wire
  • Site restoration/driveway
  • PECO scheduled for Monday

HORSHAM PFC TREATMENT SYSTEMS  SCHEDULE - GROUP 2

Status Update: 

Treatment Systems Update

For questions or to report problems: 215-672-8011