
Update: 3/20/23
Work completed since last update:
- Well 10 & 17: Site clean-up
- Well 21: Site clean-up & Installed main circuit breaker
Work projected in the upcoming week:
Well 10:
- Paint building interior
- Install main circuit breaker
Well 17:
- Paint building interior
- Install main circuit breaker
Well 21:
- Masonry work
Past Updates:
3/10/23
Work completed since last update:
- Well 10 & 17: Installed Shingles
- Well 21: No work
Work projected in the upcoming week:
- Well 10 & 17: No work
- Well 21: Site electrical work & Masonry work
3/3/23
Work completed since last update:
- Well 10 & 17: No work
- Well 21: Masonry work
Work projected in the upcoming week, weather permitting:
- Well 10 & 17: No work
- Well 21: Masonry work
2/20/23
Work completed since last update:
- Well 10 & 17: Installed roof
- Well 21: Masonry work
Work projected in the upcoming week, weather permitting:
- Well 10 & 17: Shingle installation
- Well 21: Masonry work
2/6/23
Work completed since last update
- Well 10 & 21: Masonry work
- Well 17: Began installing roof
Work projected in the upcoming week, weather permitting:
- Well 10: Roof installation
- Well 17: Complete roof installation & Begin installing building finishes
- Well 21: Masonry work
1/23/22
Work completed since last update
- Well 10: No work
- Well 17 & 21: Masonry work
Work projected in the upcoming week, weather permitting:
- Well 10 & 21: Masonry work
- Well 17: Roof installation
11/30/22
Work projected in the upcoming week:
- Well 10 & 21: No work planned
- Well 17: 24-hour pump test
Work projected in the upcoming week:
- Well 10, 17, & 21: Masonry work
11/15/22
Work completed since the last update:
- Well 10, 17, 21: No work planned
Work projected in the upcoming week:
- Well 10 & 21: No work planned
- Well 17: Perform 24-hour pump test
11/10/22
Work completed since the last update:
Well 10:
- Installed rebar in treatment building floor
- Poured treatment building floor
- Installed ductbank for electrical conduits
Well 17:
- Installed rebar in treatment building floor
- Poured treatment building floor
- Installed ductbank for electrical conduits
Well 21:
- Installed electrical vault
- Installed ductbank for electrical conduits
Work projected in the upcoming week:
Well 10:
- No work planned
Well 17:
- Preparation for post-rehabilitation 24-hour pump test
Well 21:
- Installation of masonry block
10/25/22
Work completed since the last update:
Well 10 & 17
- No work planned
Well 21:
- Began installation of electrical vault
- Began installation of ductbank for electrical conduits
Work projected in the upcoming week:
Well 10:
- Preparation for treatment building floor concrete pour
Well 17:
- Preparation for treatment building floor concrete pour
- Pour treatment building floor
- Preparation for post-rehabilitation 24-hour pump test
Well 21:
- Continue installation of electrical vault
- Continue installation of ductbank for electrical conduits
10/18/22
Work completed since the last update:
Well 10, 17 & 21:
- No work planned
Work projected in the upcoming week:
Well 10:
- Block delivery for construction of treatment building
Well 17:
- Block delivery for construction of treatment building
- Preparation for post-rehabilitation 24-hour pump test
Well 21:
- Installation of electrical vault
- Installation of ductbank for electrical conduits
10/3/22
Work completed since tha last update:
- Well 10 & 21: No work
- Well 17: Well rehabilitation
Work projected in the upcoming week:
- Well 10 & 21: No work planned until block is delivered
- Well 17: Preparation for post-rehabilitation 24-hour pump test
9/21/22
Work completed since the last update:
Well 10: No work planned
Well 17: Began well rehabilitation
Well 21:
- Poured building floor
- Performed site clean up
Work projected in the upcoming week:
Well 10 & 21: No work planned until block is delivered
Well 17: Continue well rehabilitation
9/8/22
Work completed since the last update:
Well 10 & 17: No work planned
Well 21:
- Paved Jarrett Road
- Installed rebar and concrete formwork
- Continued installation of masonry block
- Worked on site clean up
- Began electrical work
Work projected in the upcoming week:
Well 10 & 17: No work planned until block is delivered
Well 21:
- Continue site clean up and grading and seeding
- Concrete pour, weather permitting
8/30/22
Work completed since the last update:
Well 10 & 17 - No work completed
Well 21:
- Installed water line
- Installed water service
- Pressure tested water lines - all lines passed testing
Work projected in the upcoming week:
Well 10 & 17: General site work
Well 21:
- Masonry work, pending crew availability
- Electrical work, pending contractor availability
- Paving of Jarrett Road
8/2/22
Work completed since the last update:
Well 10:
- Begin masonry work
- Set catch basin and install sanitary drain line
- Pressure test water line
Well 17:
- Begin masonry work
- Set catch basin and install sanitary drain line
- Install floor drains in building
Well 21: Site preparation for upcoming week
Work projected in the upcoming week:
Well 10: Install floor drains in building
Well 17: Pressure test water line
Well 21: Install water and sewer lines from Babylon Rd to building
7/21/22
Work completed since the last update:
Well 10: Install water lines
Well 17:
- Pour building footers
- Install tap on water main
- Install water line
- Install sanitary line
Well 21:
- Install rebar and pour footers
- Begin installation of water line
- Begin installation of sanitary line
Work projected:
Well 10 & 17: No work planned
Well 21:
- Continue installation of sanitary line
- Continue installation of water line
6/21/22
Work completed since the last update:
Well 10:
- Building footer excavation
- Install rebar and pour building footers
- Masonry work
Well 17:
- Continue installation of sanitary line
- Install saddle on existing sanitary main
- Building footer excavation
- Install rebar and pour building footers
Well 21:
- Demolition & General site preparations
- Tree removal on library property
Work projected:
Well 10: Masonry work
Well 17:
- Pour building footers
- Continue installation of sanitary line
Well 21:
- Building footer excavation
- Install rebar and pour building footers
6/13/22
Work completed to date:
Well 10
- Demolition clean up
- Run new sanitary line
Well 17 & 22: No work planned
Work projected in the upcoming week:
Well 10: Footer excavation
Well 17 & 22: No work planned
5/9/22
Work completed to date:
- Well 10: Asbestos abatement, tree clearing and E&S measures, and demolition of well house
- Well 17: Asbestos abatement, E&S measures and demolition of well house
- Well 21: Asbestos abatement, installation of portable chain link fence at former well house location and demolition of well house
Work projected for the week of 5/9/22:
Well 10, 17 and 21: Well house demolition clean up
4/26/22
- The building at Well 10 was demolished on Tuesday 4/26/22. Tree removal has begun in the area surrounding the well.
- The building at Well 17 will be demolished Wednesday 4/27/22.
- The building at Well 21, will be demolished Thursday, April 28 into Friday April 29. – The contractor will be utilizing heavy equipment within Jarrett Road while the actual demolition is in progress but is aware that the road provides emergency access and will make access available should an emergency occur while the work is ongoing. Access will be maintained after-hours. The contractor is strongly mindful of the heavy pedestrian traffic to Simmons Elementary and the Library and will take precautions to ensure the health, safety and welfare of the community throughout this important project.
HWSA encourages any interested party to sign up for email updates on the project. You may do so by going to the Authority’s website at https://www.horshamwater-sewer.com/customer-updates. After entering your contact information, scroll down to the projects section and select “Wells 10, 17, 21 Treatment Systems”.
3/17/22 - The Authority has awarded a contract to Blooming Glen Contractors, to construct and install three ion-exchange treatment systems with associated treatment buildings, associated internal and external piping, site work, electrical and HVAC work. The work will be performed at three separate locations: Well 10, Well 17 and Well 21. A construction schedule for the work has not yet been established due to ongoing supply chain issues associated with COVID. In the meantime, and prior to the start of construction contractors may be noticed performing preconstruction video-taping. This is a requirement of the project contract in order to document existing conditions throughout the work area and ultimately ensure that the area is properly restored. Email updates on this project are available by signing up on our website, completing the appropriate form and selecting “Well 10, 17 and 21 – PFAS Treatment systems”.
Letters: