Projects
Sanitary Sewer Repair & Rehabilitation ProjectUpdated: February 26, 2021 - 4:01pm Update: 2/26/21 Hello. Horsham Water & Sewer Authority has contracted with North American Pipeline Services LLC for sewer rehabilitation work in your area. Work is expected for Monday March 1 st between the hours of 7 AM and 7 PM. The contractor will be using trenchless technology to renew...Read more |
Area A Flow TransferUpdated: February 26, 2021 - 2:55pm Update: 2/26/21 Work Completed between 2/21/2021 and 2/26/2021 Relocated water main in County Line Road east of Valley Road. Continued night-time sanitary sewer installation in County Line Road east of State Route 611, including rock excavation and management of groundwater encountered in the...Read more |
County Line Road Area Infrastructure Improvements ProjectUpdated: February 16, 2021 - 9:16am Update: 2/12/21 Work Completed between 2/1/2021 and 2/5/2021: Connected water services to new water mains within Marilyn Road, Lorna Drive, and Diane Avenue Projected work for week of 2/15/21: Continue water service connections to new water mains within Diane Avenue Past Updates 2/8/21 Work...Read more |
Herman Road Tank RehabilitationUpdated: February 3, 2021 - 11:06am Update: 2/3/21 Work completed between 1/19/2021 and 2/2/2021: Completed majority of finish coating of tank exterior and foundation structures. Some repairs and touch-ups will be required in the spring. Completed installation of gate valves and altitude valve. Manufacturer start-up is still to be...Read more |
MIRIA House ConnectionsUpdated: January 25, 2021 - 8:56am Update 1/21/21 - Work is scheduled to begin in early March. Exterior preconstruction videotapping is being conducted in the meantime. Property owners will be contacted directly by the contractor (DOLI) to schedule interior inspection with existing interior conditions being documented at that time...Read more |
MIRIA Main ExtensionsUpdated: January 15, 2021 - 2:27pm Updates: Information will be available soon! Past Updates:Read more |
Treatment System Update 12/6/19Updated: December 6, 2019 - 1:34pm Work Completed up to 12/5/19 Well 2 – Removed silt sock in the easement, caulked gap between backwash tank and concrete pad and repaired issue with the door for the new FRP aeration building thus finishing punch list items for this site Well 19 – Finished installation of exterior stairs and...Read more |