Projects

Well 26 Access Driveway

Updated: January 21, 2022 - 7:58am

Update: 1/19/22 Starting on Monday, January 24, 2022 roadwork within Sawyer’s Way that is necessary to accommodate the installation of the new driveway to the Authority’s well site in your neighborhood will begin. Work will be occurring between Greenwoods Drive and Forester Road. Traffic flow will...Read more

Navy House Connections Project

Updated: January 19, 2022 - 2:43pm

Update: 1/19/22 Week of 1/10/22 The contractor (Doli) continued working on service connections. 15 services were installed to homes on Norristown Rd, Sawmill Ln, Edgewood Ave, Willowbrook Rd, Evergreen Rd, Davis Grove Rd, and Avenues C and D. House connections continue to follow service connections...Read more

Fire Hydrant Replacement Project

Updated: January 19, 2022 - 2:21pm

Update: 1/18/22 Work completed the week of 1/10/22: Hydrants on Hemingway, Marietta, Midfield and Willowbrook Work projected for the week of 1/17/22: Hydrants on Marietta, Cedar Hill and Landis Past Updates: 1/11/22 Work began on Willowbrook Drive and Midfield Drive. Calabria Drive and Hemingway...Read more

Maple Avenue Tank Rehabilitation

Updated: January 12, 2022 - 8:31am

Update: 1/11/22 Valve installation has been completed and fence installation continues. Past Updates: 9/8/21 The contractor has commenced sand blasting, rehabilitation and coating work, which will continue for the next several months. 8/2/21 - Anticipated work schedule 6/22-6/28 Tree work 6/28-7/10...Read more

Herman Road Sewers

Updated: November 30, 2021 - 9:08am

Update: 11/30/21 Design work for the extension of public sewer is beginning. The design phase of the project requires field survey of Herman Road as well as the exterior features of the properties to be served by the sewer. The property features required for design include house corners, trees,...Read more

MIRIA Main Extensions

Updated: November 22, 2021 - 9:19am

Update: 11/22/21 Work Completed between 11/08/2021 and 11/18/2021 Contractor completed bacteriological testing for Davis Grove Road and Kunz Lane. Contractor installed water services on McKean Road. Contractor installed water services on Welsh Road. Contractor installed water services on Davis...Read more

MIRIA Main Extension Phase II

Updated: September 21, 2021 - 9:42am

Update: 9/21/21 Past Update: N/A Letters: 9/21/21 – Resident LetterRead more

MIRIA House Connections

Updated: September 20, 2021 - 11:39am

Update - 9/17/21 Updated schedule Past Updates 1/21/21 - Work is scheduled to begin in early March. Exterior preconstruction videotapping is being conducted in the meantime. Property owners will be contacted directly by the contractor (DOLI) to schedule interior inspection with existing interior...Read more

County Line Road Area Infrastructure Improvements Project

Updated: September 8, 2021 - 2:45pm

Update: 8/23/21 Approval of final payment and contract closeout was recommended to the Board for consideration at its business meeting on 8/23/21. Past Updates 4/27/21 Work Completed between 4/14/2021 and 4/24/2021: Performed base pavement restoration within Linda Lane, Diane Avenue, Lorna Drive,...Read more

Sanitary Sewer Repair & Rehabilitation Project

Updated: May 21, 2021 - 2:01pm

Update: 5/21/21 (schedule provided below work phase descriptions) Project Introduction Horsham Water & Sewer Authority has contracted with Vortex Services for a sanitary sewer rehabilitation project in your neighborhood. The project will be performed in phases over the course of approximately...Read more

Pages