Projects

MIRIA Main Extensions

Updated: October 18, 2021 - 10:53am

Update: 10/15/21 Work Completed between 10/4/2021 and 10/14/2021 Contractor completed installation of water main on Welsh Road. Contractor started pressure testing of McKean Rd water main. Contractor began the installation of the water main on Davis Grove Road. The directional drilling below Park...Read more

Well 26 Access Driveway

Updated: September 23, 2021 - 9:13am

Project Overview: The Authority has awarded a contract to Doli Construction Co., to install alternate driveway access to our well located in the area of Greenwoods Drive and Beaver Hill Road. Upon completion of the project, the Authority will no longer need to require parking restrictions for...Read more

MIRIA Main Extension Phase II

Updated: September 21, 2021 - 9:42am

Update: 9/21/21 Past Update: N/A Letters: 9/21/21 – Resident LetterRead more

MIRIA House Connections

Updated: September 20, 2021 - 11:39am

Update - 9/17/21 Updated schedule Past Updates 1/21/21 - Work is scheduled to begin in early March. Exterior preconstruction videotapping is being conducted in the meantime. Property owners will be contacted directly by the contractor (DOLI) to schedule interior inspection with existing interior...Read more

Maple Avenue Tank Rehabilitation

Updated: September 8, 2021 - 2:57pm

Update: 9/8/21 The contractor has commenced sand blasting, rehabilitation and coating work, which will continue for the next several months. Past Updates: 8/2/21 - Anticipated work schedule 6/22-6/28 Tree work 6/28-7/10 Mobilization/temporary fence 7/12-7/23 Containment/pipe scaffold 7/26-8/27...Read more

Herman Road Sewers

Updated: September 8, 2021 - 2:54pm

Update: 8/31/21 On 8/23/21, Horsham Water & Sewer Authority’s Board voted to proceed with planning and design of a sewer extension that will serve 11 properties within a segment of Horsham Road between Brantford Circle and Downey Drive that does not currently have access to public sewer. The...Read more

County Line Road Area Infrastructure Improvements Project

Updated: September 8, 2021 - 2:45pm

Update: 8/23/21 Approval of final payment and contract closeout was recommended to the Board for consideration at its business meeting on 8/23/21. Past Updates 4/27/21 Work Completed between 4/14/2021 and 4/24/2021: Performed base pavement restoration within Linda Lane, Diane Avenue, Lorna Drive,...Read more

Sanitary Sewer Repair & Rehabilitation Project

Updated: May 21, 2021 - 2:01pm

Update: 5/21/21 (schedule provided below work phase descriptions) Project Introduction Horsham Water & Sewer Authority has contracted with Vortex Services for a sanitary sewer rehabilitation project in your neighborhood. The project will be performed in phases over the course of approximately...Read more

Area A Flow Transfer

Updated: May 10, 2021 - 12:16pm

Update: 5/10/21 Work Completed between 5/3/21 and 5/7/21 Continued roadway restoration in County Line Road. Completing flushing and continued testing in easement areas off County Line Road. Work Projected for week of 5/10/21 Continue restoration in easement areas and along County Line Road...Read more

500 Block Moreland Avenue Sewer Evaluation

Updated: March 9, 2021 - 3:17pm

Update: 3/9/21 - PADEP has directed HWSA to evaluate the need for public sewer in this area. In 2016-2017 HWSA performed a survey to gauge property owner interest in the Authority constructing a sewer extension. At that time, there was not a majority interest so the Authority did not move forward...Read more

Pages