Projects

Well 10, 17 and 21 - PFAS Treatment Systems

Updated: June 21, 2022 - 3:51pm

Project Overview: 6/21/22 Work completed since the last update: Well 10: Building footer excavation Install rebar and pour building footers Masonry work Well 17: Continue installation of sanitary line Install saddle on existing sanitary main Building footer excavation Install rebar and pour...Read more

Fire Hydrant Replacement Project

Updated: May 9, 2022 - 1:59pm

Update: 5/9/22 Work previously completed: Hydrants replaced on Calabria Lane, Hemingway Drive and Cedar Hill Road Work Scheduled for week of 5/9/22: Hydrants will be replaced on Lower State Road and Charter Lane Past Updates: 3/17/22 Week of 3/7/22 Hydrant installation occurred on Cedar Hill Road...Read more

Well 26 Access Driveway

Updated: April 6, 2022 - 2:42pm

Update: 4/6/22 Work Completed between 3/21/22 to 3/31/22 Site restoration and abandonment of re-routed utilities Curb installation and preparing driveway site layout Work Projected for week of 4/4/22 Driveway pavement installation Site restoration and erosion control measures Past Updates: 2/15/22...Read more

Navy House Connections Project

Updated: March 15, 2022 - 6:57am

Update: 3/15/22 Week of 3/7/22 Final well abandonments were completed Future work All necessary restoration will take place in the spring, as weather permits Past Updates: 3/2/22 Week of 2/21/22 The well driller abandoned eight wells. All houses are connected. Week of 2/28/22 Well abandonments will...Read more

Maple Avenue Tank Rehabilitation

Updated: January 12, 2022 - 8:31am

Update: 1/11/22 Valve installation has been completed and fence installation continues. Past Updates: 9/8/21 The contractor has commenced sand blasting, rehabilitation and coating work, which will continue for the next several months. 8/2/21 - Anticipated work schedule 6/22-6/28 Tree work 6/28-7/10...Read more

Herman Road Sewers

Updated: November 30, 2021 - 9:08am

Update: 11/30/21 Design work for the extension of public sewer is beginning. The design phase of the project requires field survey of Herman Road as well as the exterior features of the properties to be served by the sewer. The property features required for design include house corners, trees,...Read more

MIRIA Main Extensions

Updated: November 22, 2021 - 9:19am

Update: 11/22/21 Work Completed between 11/08/2021 and 11/18/2021 Contractor completed bacteriological testing for Davis Grove Road and Kunz Lane. Contractor installed water services on McKean Road. Contractor installed water services on Welsh Road. Contractor installed water services on Davis...Read more

MIRIA Main Extension Phase II

Updated: September 21, 2021 - 9:42am

Update: 9/21/21 Past Update: N/A Letters: 9/21/21 – Resident LetterRead more

MIRIA House Connections

Updated: September 20, 2021 - 11:39am

Update - 9/17/21 Updated schedule Past Updates 1/21/21 - Work is scheduled to begin in early March. Exterior preconstruction videotapping is being conducted in the meantime. Property owners will be contacted directly by the contractor (DOLI) to schedule interior inspection with existing interior...Read more

County Line Road Area Infrastructure Improvements Project

Updated: September 8, 2021 - 2:45pm

Update: 8/23/21 Approval of final payment and contract closeout was recommended to the Board for consideration at its business meeting on 8/23/21. Past Updates 4/27/21 Work Completed between 4/14/2021 and 4/24/2021: Performed base pavement restoration within Linda Lane, Diane Avenue, Lorna Drive,...Read more

Pages