Projects

Sanitary Sewer Repair & Rehabilitation Project

Updated: May 7, 2021 - 10:02am

Update: 5/7/21 (schedule provided below work phase descriptions) Project Introduction Horsham Water & Sewer Authority has contracted with Vortex Services for a sanitary sewer rehabilitation project in your neighborhood. The project will be performed in phases over the course of approximately...Read more

Area A Flow Transfer

Updated: April 30, 2021 - 3:15pm

Update: 4/30/21 Work Completed between 4/26/2021 and 4/30/2021 Continued roadway restoration in County Line Road including intersection of Easton Road. Continued sewer flushing and testing in easement area off County Line Road. Work Projected for week of 5/3/21 Continuing sewer flushing and testing...Read more

County Line Road Area Infrastructure Improvements Project

Updated: April 27, 2021 - 12:59pm

Update: 4/27/21 Work Completed between 4/14/2021 and 4/24/2021: Performed base pavement restoration within Linda Lane, Diane Avenue, Lorna Drive, and Marilyn Road. Contractor reviewed areas for concrete curb and apron restoration with G&A engineer and observer. Work projected for week of 4/26/...Read more

500 Block Moreland Avenue Sewer Evaluation

Updated: March 9, 2021 - 3:17pm

Update: 3/9/21 - PADEP has directed HWSA to evaluate the need for public sewer in this area. In 2016-2017 HWSA performed a survey to gauge property owner interest in the Authority constructing a sewer extension. At that time, there was not a majority interest so the Authority did not move forward...Read more

MIRIA House Connections

Updated: March 3, 2021 - 9:10am

Update 1/21/21 - Work is scheduled to begin in early March. Exterior preconstruction videotapping is being conducted in the meantime. Property owners will be contacted directly by the contractor (DOLI) to schedule interior inspection with existing interior conditions being documented at that time...Read more

Herman Road Tank Rehabilitation

Updated: February 3, 2021 - 11:06am

Update: 2/3/21 Work completed between 1/19/2021 and 2/2/2021: Completed majority of finish coating of tank exterior and foundation structures. Some repairs and touch-ups will be required in the spring. Completed installation of gate valves and altitude valve. Manufacturer start-up is still to be...Read more

MIRIA Main Extensions

Updated: January 15, 2021 - 2:27pm

Updates: Information will be available soon! Past Updates:Read more

Treatment System Update 12/6/19

Updated: December 6, 2019 - 1:34pm

Work Completed up to 12/5/19 Well 2 – Removed silt sock in the easement, caulked gap between backwash tank and concrete pad and repaired issue with the door for the new FRP aeration building thus finishing punch list items for this site Well 19 – Finished installation of exterior stairs and...Read more