Projects
Well 10, 17 and 21 - PFAS Treatment SystemsUpdated: March 20, 2023 - 4:13pm Update: 3/20/23 Work completed since last update: Well 10 & 17: Site clean-up Well 21: Site clean-up & Installed main circuit breaker Work projected in the upcoming week: Well 10: Paint building interior Install main circuit breaker Well 17: Paint building interior Install main circuit...Read more |
Herman Road SewersUpdated: March 17, 2023 - 3:29pm Update: 3/17/23 Work Completed since the last Update: Continued laying pipe Work Projected in the Upcoming Week: Continue laying pipe Install manhole Past Updates: 3/10/23 Work Completed since the last Update: Continued laying pipe to manhole Work Projected in the Upcoming Week: Continue laying...Read more |
Sanitary Sewer Rehabilitation 2023Updated: February 27, 2023 - 11:12am Update: 2/27/23 - On Wednesday 3/1/23, crews will be performing CCTV in the sewer mains on Harcourt Lane and Butternut Drive Past Updates: 2/6/23 During the week of 2/6/23, crews will be on the following streets: Butternut Drive Holly Drive Springbrook Lane County Line Road Also, there will be a...Read more |
500 Block Moreland Avenue Sewer ExtensionUpdated: February 22, 2023 - 10:17am Update: 2/21/23 - Past Updates 3/9/21 - PADEP has directed HWSA to evaluate the need for public sewer in this area. In 2016-2017 HWSA performed a survey to gauge property owner interest in the Authority constructing a sewer extension. At that time, there was not a majority interest so the Authority...Read more |
441-503 Privet Road SewersUpdated: February 21, 2023 - 12:31pm Update: 2/21/22 - Surveying for this project is anticipated to occur during the week of February 21st or Feburary 27th. Past Updates: 11/9/22 HWSA conducted a survey between September and November 2022 and on November 7, 2022, the Board determined to move forward with the design for the project...Read more |
Norristown Road Test WellUpdated: February 21, 2023 - 12:27pm coming soonRead more |
Witmer Road Tank RehabilitationUpdated: January 25, 2023 - 9:56am Update: 1/25/23 - The Authority recently awarded a contract for the rehabilitation and painting of the water tank located on Witmer Road. The contract has been awarded to Dynamic Sandblasting and Painting LLC of Eatontown, NJ. Mobilization to the site has begun and work is currently anticipated to...Read more |
Area A Flow TransferUpdated: January 24, 2023 - 12:09pm Update: 1/24/23 Breaking News! County Line Road Lane Restrictions - On Thursday January 26, 2023, DOLI Construction will be preforming road work on County Line Road at the intersection of Valley Road. Lane restrictions will be in place between the hours of 9AM and 3PM. Delays associated with...Read more |
Butternut/Holly Drives Watermain Replacement 2023Updated: January 9, 2023 - 12:32pm Updates: 1/6/23 - The Authority will be replacing the water main and performing rehabilitation work on the sewer in your neighborhood. The Authority budgets annually for replacement/rehabilitation of aging infrastructure and this work is part of that ongoing program. The Authority has determined...Read more |
MIRIA House Connections Phase 2Updated: November 22, 2022 - 4:04pm Update: 11/22/22 The Authority has awarded a contract to DOLI Construction Corporation, of Chalfont, PA to perform connections to the public water supply. The scope of work includes the installation of a service connection to the existing water main fronting individual properties, connection of the...Read more |